Interstate 93 Transportation Study

Project Scope

Vacant land for a possible station site in Manchester NHThe project scope will include three phases of work over a 20-month period.  Phase 1 will include the developing of the Purpose and Need statement, setting goals and objectives, identifying issues, developing and implementing a Public Involvement Plan, collecting and analyzing data, and developing the initial alternatives.  Phase 2 will include refining alternatives, developing draft recommendations, and developing the travel demand model and alternative analysis.  Phase 3 will include developing and presenting a strategic plan. 

A general outline of the scope is listed below:

1: Purpose and Need, alternatives development

1.1: Review studies, reports; summary

1.2: Identify, evaluate existing data

1.3: Research legal, institutional, land-use policy dependencies potentially impacting transit implementation

1.4: Develop outreach plan

1.5: Two public meetings

1.6: Meet interested parties; 20 in Phase I

1.7: Purpose and Need statement

1.8: Identify initial alternatives

2: Refinement, screening of alternatives

2.1: Land-use policy report

2.1.1: Baseline report; existing conditions

2.1.2: Transit-supportive policy alternatives

2.1.3: Station-area development potential

2.1.4: Impact of land-use policy scenarios

2.2: Alternatives evaluation criteria

2.3: Define conceptual alternatives (up to eight): HOV, rail, TSM, BRT

2.4: Evaluation

2.5: Present to committees

2.6: Finalize, alternatives

2.7: Benefits, impacts: economic, environmental, cultural, secondary growth

2.8: Two informational meetings

2.9: Develop TDF model – based on Nashua model

2.10: Alternative forecasts

2.11: TDF report

2.12: Define Tier 2 alternatives (up to four)

2.13: Evaluate alternatives

2.14: Three conceptual station design approaches

2.15: Define, illustrate TOD opportunities

2.16: Benefits, impacts

2.17: “Regulatory framework report”

3: Strategic implementation plan

3.1: Committee discussion

3.2: Draft plan, including financial plan

3.3: Public information meetings

3.4: Advisory committee approval

3.5: Finalize plan, including study deliverables

A complete project scope of work is available that outlines the tasks that are to be performed over the 20-month I-93 Transit Investment Study.        